Kuma

Zentralbahn

Year of manufacture

2019

Kummler+Matter Services

Complete dismantling and installation of the catenary for a three-track station

Route length

-

Short description

In a concentrated construction process, the entire catenary for the station was dismantled and then rebuilt in three phases. It was also necessary to ensure that the tracks were navigable again every morning. The Horw support structure was also entirely rebuilt and renewed.